Master Scheduling and Material Requirements Planning MCQ
A ______ is useful way to represent the bill of materials file that shows the product hierarchy and the explosion into its parts.
Answer
Correct Answer:
Product structure tree
Note: This Question is unanswered, help us to find answer for this one
In a ______ system, unanticipated demand for products may hamper production because there is a lack of sufficient capacity.
Answer
Correct Answer:
Just-in-time
Note: This Question is unanswered, help us to find answer for this one
The ______ provides information on the number of units required for an end-product for specific time periods of the planning horizon.
Answer
Correct Answer:
Master production schedule
Note: This Question is unanswered, help us to find answer for this one
______ systems have the required materials and components available when needed for the production of finished goods based on forecasted requirements.
Answer
Correct Answer:
Materials requirement planning
Note: This Question is unanswered, help us to find answer for this one
______ reports call managers’ attention to major problems such as overdue and late orders, excessive scrap rates, reporting errors, and requirements for nonexistent parts.
Answer
Correct Answer:
Exception
Note: This Question is unanswered, help us to find answer for this one
______ approach allows selection of the number of periods covered by an order or setup such that the holding cost over the covered horizon is approximately equal to the ordering or setup cost.
Answer
Correct Answer:
Part-period balancing
Note: This Question is unanswered, help us to find answer for this one
______ system is best suited for a repetitive production process that produces similar products that have stable demand.
Answer
Correct Answer:
Just-in-time
Note: This Question is unanswered, help us to find answer for this one
______ reports can be used to forecast future inventory requirements.
Answer
Correct Answer:
Planning
Note: This Question is unanswered, help us to find answer for this one
The ______ leads to a manufacturing plan that determines the quantity of each end item to be produced in specific periods of the short-range planning horizon.
Answer
Correct Answer:
Master scheduling process
Note: This Question is unanswered, help us to find answer for this one
______ systems focus on detailed scheduling of production in response to actual orders.
Answer
Correct Answer:
Just-in-time
Note: This Question is unanswered, help us to find answer for this one
______ contains the records of all items in inventory, including on-hand inventory and scheduled receipts.
Answer
Correct Answer:
Inventory status file
Note: This Question is unanswered, help us to find answer for this one
Material requirements planning systems can use ______ to minimize uncertainty associated with production or supply lead times.
Answer
Correct Answer:
Backflushing
Note: This Question is unanswered, help us to find answer for this one
Regenerative MRP systems are suitable for production systems that are relatively stable and have the advantage of ______ processing costs.
Answer
Correct Answer:
Lower
Note: This Question is unanswered, help us to find answer for this one
_____ is a planning system for dependent demand items.
Answer
Correct Answer:
Materials requirement planning
Note: This Question is unanswered, help us to find answer for this one
______ is the process of scheduling and describing the receipt of inventories of materials, components, subassemblies
Answer
Correct Answer:
Time phasing
Note: This Question is unanswered, help us to find answer for this one
Time frame in which the master schedule may be accommodated with trade-offs is known as
Answer
Correct Answer:
Slushy time fence
Note: This Question is unanswered, help us to find answer for this one
SRP is stands for
Answer
Correct Answer:
Service requirements planning
Note: This Question is unanswered, help us to find answer for this one
A strategy to combat uncertainty associated with supply or production lead times is known as
Answer
Correct Answer:
Safety lead time
Note: This Question is unanswered, help us to find answer for this one
Rolling schedule updating the schedule when moving forward in time by capturing the impact of actual transactions
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Regenerative system a system in which the _______ of the MRP records is performed periodically, most commonly every week
Answer
Correct Answer:
Updating or replanning
Note: This Question is unanswered, help us to find answer for this one
A way to represent the BOM file that shows the product hierarchy and the explosion into its parts is called
Answer
Correct Answer:
Product structure tree
Note: This Question is unanswered, help us to find answer for this one
Which schedules delineate the quantity and timing of future material orders ?
Answer
Correct Answer:
Planned order schedules
Note: This Question is unanswered, help us to find answer for this one
A reports that specify when an order quantity for an item will be released to a vendor or an in-house production facility is known as
Answer
Correct Answer:
Planned order releases
Note: This Question is unanswered, help us to find answer for this one
Pegging capability that can identify the ______ item that has generated the component requirements for that item
Answer
Correct Answer:
Particular parent
Note: This Question is unanswered, help us to find answer for this one
______ lot-sizing technique in which both order (or production) quantity and time between orders (or setups) are allowed to vary.
Answer
Correct Answer:
Part-period balancing
Note: This Question is unanswered, help us to find answer for this one
A system in which replanning is done continuously, whenever changes occur in the MRP records is known as
Answer
Correct Answer:
Net-change system
Note: This Question is unanswered, help us to find answer for this one
Nervousness instability in the MRP system
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
______ is the process by which the MRP system calculates the gross and net requirements of all components and materials.
Answer
Correct Answer:
MRP explosion
Note: This Question is unanswered, help us to find answer for this one
A computer-based system that translates the end item requirements of the master schedule into subassemblies, components, and raw materials is known as
Answer
Correct Answer:
Material requirements planning
Note: This Question is unanswered, help us to find answer for this one
The process that determines the quantities of each end item to be produced in specific periods during a specific planning horizon is known as
Answer
Correct Answer:
Master scheduling
Note: This Question is unanswered, help us to find answer for this one
An individual production quantities of the end items to be produced at various periods of a given planning horizon is known as
Answer
Correct Answer:
Master production schedule
Note: This Question is unanswered, help us to find answer for this one
_________ is a inventory stocking location right on the shop floor
Answer
Correct Answer:
Manufacturing supermarket
Note: This Question is unanswered, help us to find answer for this one
lot-sizing technique used the techniques in which the amount ordered or produced is the same as the demand requirements for the MRP items
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Lot size the predetermined quantity of an item that is either ______or ______ from a supplier
Answer
Correct Answer:
Manufactured or purchased
Note: This Question is unanswered, help us to find answer for this one
Inventory status file contains the records of all items in inventory, including on-hand inventory and scheduled receipts
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
the portion of the master schedule in which no changes to the schedule can be accommodated unless a senior executive requests such changes is known as
Answer
Correct Answer:
Frozen time fence
Note: This Question is unanswered, help us to find answer for this one
Choose correct option about Flexible time fence
Answer
Correct Answer:
Portion of the master schedule time horizon that is farthest out in the future and changes can be easily accommodated
Note: This Question is unanswered, help us to find answer for this one
Fixed-period ordering is a technique in which orders for the MRP items are placed at fixed periods
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
_______ is an orders that are not changed automatically when conditions change, usually requiring approval from a senior manager
Answer
Correct Answer:
Firm planned orders
Note: This Question is unanswered, help us to find answer for this one
Which system material requirements are specified on a daily basis or by shift
Answer
Correct Answer:
Bucketless
Note: This Question is unanswered, help us to find answer for this one
________ that contains the complete listing of all assemblies, subassemblies, parts and components
Answer
Correct Answer:
Bill of materials
Note: This Question is unanswered, help us to find answer for this one
BOL stands for
Answer
Correct Answer:
Bill of labor
Note: This Question is unanswered, help us to find answer for this one
(In backflushing) BOM is exploded to determine the quantities of component parts, material, and subassemblies that were used to make the item
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Available-to-promise (ATP) invento physically on hand that can be realistically promised for new customer order deliveries
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one