Industrial Engineering and Production Management MCQ
Industrial Engineering and Production Management MCQ
1. An internal analysis, the third step of the strategic management process helps identify ________.
Answer
Correct Answer:
Resources and capabilities
Note: This Question is unanswered, help us to find answer for this one
2. When slack of an activity is negative
Answer
Correct Answer:
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Note: This Question is unanswered, help us to find answer for this one
3. For material transportation, conveyors are used when the prevailing conditions include
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one
4. In value engineering, the term value refers to
Answer
Correct Answer:
Utility of the product
Note: This Question is unanswered, help us to find answer for this one
5. Job evaluation is the method of determining the
Answer
Correct Answer:
Relative values of a job
Note: This Question is unanswered, help us to find answer for this one
6. In A-B-C analysis, which class of items are generally large in number?
Note: This Question is unanswered, help us to find answer for this one
7. Which of the following statement is correct?
Answer
Correct Answer:
A-B-C analysis is based on Pareto's principle.
Note: This Question is unanswered, help us to find answer for this one
8. Which one of the following chart gives simultaneously information about the progress of work and machine loading?
Answer
Correct Answer:
Man-machine chart
Note: This Question is unanswered, help us to find answer for this one
9. Production cost refers to prime cost plus
Answer
Correct Answer:
Factory, administration, sales overheads and profit
Note: This Question is unanswered, help us to find answer for this one
10. The type of organisation preferred for a steel industry, is
Answer
Correct Answer:
Line, staff and functional organisation
Note: This Question is unanswered, help us to find answer for this one
11. Fixed position layout is also known as
Answer
Correct Answer:
Static product layout
Note: This Question is unanswered, help us to find answer for this one
12. Valve analysis is particularly of interest when
Answer
Correct Answer:
Production is on large scale
Note: This Question is unanswered, help us to find answer for this one
13. Probabilistic time for completion of any activity can be found out from
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one
14. A critical activity has
Answer
Correct Answer:
Zero slack
Note: This Question is unanswered, help us to find answer for this one
15. PERT is an event oriented technique.
Note: This Question is unanswered, help us to find answer for this one
16. Scheduling
Answer
Correct Answer:
Determines the programme for the operations
Note: This Question is unanswered, help us to find answer for this one
17. Micromotion study is
Answer
Correct Answer:
Subdivision of an operation into therbligs and their analysis
Note: This Question is unanswered, help us to find answer for this one
18. F. W. Taylor introduced a system of organisation known as
Answer
Correct Answer:
Functional organisation
Note: This Question is unanswered, help us to find answer for this one
19. The correct sequence of phases in value engineering is
Answer
Correct Answer:
Creative phase, information phase, investigation phase, evaluation phase
Note: This Question is unanswered, help us to find answer for this one
20. A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
Note: This Question is unanswered, help us to find answer for this one
21. The purpose of micromotion study is to
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one
Mechanical Engineering MCQs | Topic-wise