1. A synonym for tasks or activities that represent the basic unit of work used to develop the project schedule is called Work Package.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
2. Amount of work that must be performed to complete the task is known as:
Answer
Correct Answer:
Work Content
Note: This Question is unanswered, help us to find answer for this one
3. A hierarchical description of the project work content that begins with the major deliverables and shows the work associated with the delivery of these end product(s)/service(s) subdivided into elemental work packages or tasks is called ___________.
Answer
Correct Answer:
Work Breakdown Structure (WBS)
Note: This Question is unanswered, help us to find answer for this one
4. Time-Dependent costs is a project-related cost that varies directly with the duration of the project.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
5. _____________ is a process whose behavior is described by some probability distribution.
Answer
Correct Answer:
Stochastic Process
Note: This Question is unanswered, help us to find answer for this one
6. Any expense directly associated with performing a specific task or activity; also known as direct costs is known as:
Answer
Correct Answer:
Resource Costs
Note: This Question is unanswered, help us to find answer for this one
7. A standardized set of parameters for projects are called ___________ .
Answer
Correct Answer:
Project Template
Note: This Question is unanswered, help us to find answer for this one
8. Precedence relationships Constraints on the order in which tasks must be performed.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
9. Parametric is an estimation approach that identifies the causal factors that determine work content and builds a mathematical model relating which estimation factors:
Answer
Correct Answer:
ALL of these
Note: This Question is unanswered, help us to find answer for this one
10. Individuals who are managers and technical experts drawn from the relevant areas of the business brought together to come to a consensus on estimates
Answer
Correct Answer:
Panel of Experts
Note: This Question is unanswered, help us to find answer for this one
11. ________ is the cost and duration of a task when the direct resource costs are minimized.
Answer
Correct Answer:
Normal Point
Note: This Question is unanswered, help us to find answer for this one
12. Any payment made as a result of completing a project before or after a stated due date is known as :
Answer
Correct Answer:
Incentive Payment
Note: This Question is unanswered, help us to find answer for this one
13. Full-Time Equivalents (FTEs) the amount of work effort associated with a full-time resource.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
14. _____________ individual perceptions and beliefs that cause individuals to over- or underestimate forecasted values.
Answer
Correct Answer:
Estimation bias
Note: This Question is unanswered, help us to find answer for this one
15. Deterministic means refer to an assumption that the values of a forecasted metric are known with complete certainty.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
16. Delphi method is an estimation approach in which a panel of experts anonymously submit contributions and then assess the contributions as a whole is called ______________ .
Answer
Correct Answer:
Delphi Method
Note: This Question is unanswered, help us to find answer for this one
17. Indicates the minimum possible duration of a task or project and the associated costs is known as:
Answer
Correct Answer:
Crash Point
Note: This Question is unanswered, help us to find answer for this one
18. Composite estimate is an estimate gathered from a panel of experts, then averaged into a composite estimate.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
19. Bounded distribution is a distribution with __________ .
Answer
Correct Answer:
Limiting values
Note: This Question is unanswered, help us to find answer for this one
20. Activities are the set of elemental tasks that are the basis for ___________ the project.
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one