________________ is the concept of inserting time buffers into a schedule to develop stable proactive schedules that can withstand some risks.
Answer
Correct Answer:
Robust Scheduling
Note: This Question is unanswered, help us to find answer for this one
Reactive schedule means no explicit schedule is used; the project tasks simply proceed at a predefined rate.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Proactive schedule is a baseline schedule developed during the planning phase in such a way as to protect against schedule disruptions is called _________.
Answer
Correct Answer:
Proactive Schedule
Note: This Question is unanswered, help us to find answer for this one
An acronym for program evaluation and review technique (may also be project evaluation and review technique) is known as:
Answer
Correct Answer:
PERT
Note: This Question is unanswered, help us to find answer for this one
______________ is a process that repeatedly sets values for each random variable by sampling (with replacement) from each variable’s respective distribution.
Answer
Correct Answer:
Monte Carlo Simulation
Note: This Question is unanswered, help us to find answer for this one
The longest path in a project’s precedence network when task expected durations is known :
Answer
Correct Answer:
Expected Critical Path (ECP)
Note: This Question is unanswered, help us to find answer for this one
A planned cost contingency used to protect the project budget against the impact of unplanned tasks and task overruns is called ____________.
Answer
Correct Answer:
Cost/Work Buffer
Note: This Question is unanswered, help us to find answer for this one