Home > MCQs > Finance & Management > Microsoft Project MCQs

Microsoft Project MCQ

Quizack provides the greatest Microsoft Project questions for you to learn quickly. Quizack went to great lengths to ensure that you could study the most recent Microsoft Project MCQ questions. Quizack has together with the most modern interactive engines for you, so you can study without interruption.

Microsoft Project Quick Quiz

Question 1 of 10
  • If you click Fixed Work in the Task type list, you cannot change the Effort driven setting for the task.

    Answer & Explanation

    Correct Answer: True

    Note: This Question is unanswered, help us to find answer for this one

  • You are working with subproject files (the master project file is not open) and have saved the changes you made. What happens to the master project when it is opened?

    Answer & Explanation

    Correct Answer: The master project will reflect the changes made to the subproject files.

    Note: This Question is unanswered, help us to find answer for this one

  • If you want to change the hierarchical structure of a task or subtask as part of an outline structure for your project, you need to change the task type or add a deadline date rather than indent or outdent the task.

    Answer & Explanation

    Correct Answer: False

    Note: This Question is unanswered, help us to find answer for this one

  • A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays?

    Answer & Explanation

    Correct Answer: On the Project tab, click Move Project.

    Note: This Question is unanswered, help us to find answer for this one

  • Which option is not available in the Report tab on the ribbon?

    Answer & Explanation

    Correct Answer: Network Diagram

    Note: This Question is unanswered, help us to find answer for this one

  • How does Microsoft Project calculate work?

    Answer & Explanation

    Correct Answer: Duration x Units = Work

    Note: This Question is unanswered, help us to find answer for this one

  • What is CPI=?

    Answer & Explanation

    Correct Answer: EV/AC

    Note: This Question is unanswered, help us to find answer for this one

  • Which of the following is NOT a valid import type for tasks?

    Answer & Explanation

    Correct Answer: SAP ALV grid

    Note: This Question is unanswered, help us to find answer for this one

  • The _______ is used as a template for other calendars.

    Answer & Explanation

    Correct Answer: Base calendar

    Note: This Question is unanswered, help us to find answer for this one

  • You want to change the view of the timescale on Gantt chart to be more granular. How many tiers does the timescale support?

    Answer & Explanation

    Correct Answer: Ten

    Note: This Question is unanswered, help us to find answer for this one

  • Microsoft Project Quick Quiz

    battery

    Poor Results!

    You need a lot of improvement.

    Just don't give up!

    Correct Answers: 0/10

    Start Practicing with our MCQs given below.