1. You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?
Answer
Correct Answer:
Finish-to-Finish (FF)
Note: This Question is unanswered, help us to find answer for this one
2. You are modifying a project's work breakdown structure (WBS) code. What is the default length for any selected sequence type?
Answer
Correct Answer:
Any
Note: This Question is unanswered, help us to find answer for this one
3. A resource's hours have increased over the span of five days for a particular task. The duration has not changed, and the task is effort driven. What element can you add to the Task Usage view to see what has changed?
Answer
Correct Answer:
Add a column for the Peak value.
Note: This Question is unanswered, help us to find answer for this one
4. When breaking down the work that needs to be done on a project, what is the smallest unit of work known as?
Answer
Correct Answer:
Work package
Note: This Question is unanswered, help us to find answer for this one
5. You are using work breakdown structure (WBS) codes for an in-progress project. Due to some schedule changes, tasks have been moved around, which has modified the WBS. How do you fix the WBS codes?
Answer
Correct Answer:
From the Project tab on the ribbon, click WBS > Renumber.
Note: This Question is unanswered, help us to find answer for this one
6. Ou have several Microsoft Project files open. One contains sensitive information, so you hide that file. What is true regarding the hidden file?
Answer
Correct Answer:
To unhide the file, select Switch Window.
Note: This Question is unanswered, help us to find answer for this one
7. A project contains numerous linked tasks. What is the name for a task that is controlled or driven by another task(s)?
Answer
Correct Answer:
Successor
Note: This Question is unanswered, help us to find answer for this one
8. When you create a new blank project in Microsoft Project, what is the default view?
Answer
Correct Answer:
Gantt Chart with Timeline
Note: This Question is unanswered, help us to find answer for this one
9. You want to manage multiple projects with one project designated as the master project. Which button on the ribbon do you use?
Answer
Correct Answer:
Subproject
Note: This Question is unanswered, help us to find answer for this one
10. You are working with a master project that contains subprojects, and you want to see a list of tasks on which a subproject file is dependent. How can you do this in Microsoft Project?
Answer
Correct Answer:
On the Project tab, click Subproject.
Note: This Question is unanswered, help us to find answer for this one
11. You are working with two project files. You want the second project to contain some of the same tasks, along with their work assignments, as the first project. You Choose to copy the tasks between the projects. What else is copied along with the task when performing basic copy and paste action?
Answer
Correct Answer:
Resources
Note: This Question is unanswered, help us to find answer for this one
12. You want to change the view of the timescale on Gantt chart to be more granular. How many tiers does the timescale support?
Answer
Correct Answer:
Ten
Note: This Question is unanswered, help us to find answer for this one
13. A project currently has a software developer performing two tasks at the same time. The first task is 5 days long; the second task is day long. It has been decided that the developer can take some time to work on the shorter task in the middle the longer task without impacting the schedule. What is the best way to this!
Answer
Correct Answer:
Split the longer task to accommodate the shorter task.
Note: This Question is unanswered, help us to find answer for this one
14. A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have?
Answer
Correct Answer:
Five
Note: This Question is unanswered, help us to find answer for this one
15. On your computer, Automatically add new views, tables. filters. and groups to the global is selected. You are using a custom filter that you created in one of your schedules, and you modify it to better meet your needs. You now notice that this modification is not available in other schedules. How do you fix this?
Answer
Correct Answer:
Using Compare Projects, select the appropriate options from the Task Table and Resource Table lists.
Note: This Question is unanswered, help us to find answer for this one
16. You need to modify a resource pool. When opening the file that contains the pool, which option is not valid?
Answer
Correct Answer:
Open as read-only and allow others to use the pool.
Note: This Question is unanswered, help us to find answer for this one
17. You are working with subproject files (the master project file is not open) and have saved the changes you made. What happens to the master project when it is opened?
Answer
Correct Answer:
The master project will reflect the changes made to the subproject files.
Note: This Question is unanswered, help us to find answer for this one
18. A task has a fixed duration If the units on the task are changed, what value for the task will automatically change as a result?
Answer
Correct Answer:
Work
Note: This Question is unanswered, help us to find answer for this one
19. How many default base calendars does Microsoft Project set up for a project?
Answer
Correct Answer:
Three
Note: This Question is unanswered, help us to find answer for this one
20. A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays?
Answer
Correct Answer:
On the Project tab, click Move Project.
Note: This Question is unanswered, help us to find answer for this one
21. You have many tasks in a project file and want to convert them into milestones. How can you do this?
Answer
Correct Answer:
Change the tasks' duration to 0.
Note: This Question is unanswered, help us to find answer for this one
22. How do you mark a task's progress and have that progress reflected in the task's summary task?
Answer
Correct Answer:
Use the Task tool en the ribbon's Task tab for the summary task.
Note: This Question is unanswered, help us to find answer for this one
23. A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?
Answer
Correct Answer:
Use the Leveling Gantt view adjust the edays field for the second task.
Note: This Question is unanswered, help us to find answer for this one
24. You are preparing a meal comprising a main dish and multiple side dishes. You want the finish of the main dish to drive the finish of the side dishes. The main dish will start before and take longer than the side dishes. You need to create a link from the main dish to each of the side dishes. Which link type is appropriate?
Answer
Correct Answer:
Finish-to-Finish(FF)
Note: This Question is unanswered, help us to find answer for this one
25. A report for Earned Value Over Time has been requested, You decide to use a Microsoft Project visual report. What values does this report template compare when run?
Answer
Correct Answer:
Earned Value. Planned Value, and Actual
Note: This Question is unanswered, help us to find answer for this one
26. What is another name for a work breakdown structure?
Answer
Correct Answer:
A hierarchy of tasks
Note: This Question is unanswered, help us to find answer for this one
27. A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
Answer
Correct Answer:
It has changed to 125%.
Note: This Question is unanswered, help us to find answer for this one
28. You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?
Answer
Correct Answer:
Yes to All
Note: This Question is unanswered, help us to find answer for this one
29. Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?
Answer
Correct Answer:
Tasks and resources
Note: This Question is unanswered, help us to find answer for this one
30. In a project, duration can have different units. Which duration unit is not valid?
Answer
Correct Answer:
Quarters
Note: This Question is unanswered, help us to find answer for this one
31. You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?
Answer
Correct Answer:
Must Finish On
Note: This Question is unanswered, help us to find answer for this one
32. You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?
Answer
Correct Answer:
Critical tasks are indicated in red and other tasks are indicated in blue.
Note: This Question is unanswered, help us to find answer for this one
33. You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?
Answer
Correct Answer:
Calculate project after each edit is set to Off.
Note: This Question is unanswered, help us to find answer for this one
34. Which option is not available in the Report tab on the ribbon?
Answer
Correct Answer:
Network Diagram
Note: This Question is unanswered, help us to find answer for this one
35. A project contains many elements. What is used to describe the sum of the work required?
Answer
Correct Answer:
Work breakdown structure
Note: This Question is unanswered, help us to find answer for this one
36. You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?
Answer
Correct Answer:
Project Information
Note: This Question is unanswered, help us to find answer for this one
37. When setting the Calculate multiple critical paths option in a master project's Advanced settings, which statement is correct?
Answer
Correct Answer:
Subprojects will have critical paths calculated individually.
Note: This Question is unanswered, help us to find answer for this one
38. Which of the following defines the project scope in terms of deliverables and components, and provides the framework on which the project status is based?
Answer
Correct Answer:
Work breakdown structure
Note: This Question is unanswered, help us to find answer for this one
39. You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?
Answer
Correct Answer:
Use the Display tab in the Project Options dialog box to enable the Entry Bar.
Note: This Question is unanswered, help us to find answer for this one
40. Where can you set fixed duration, effort driven, and manually scheduled?
Answer
Correct Answer:
Task form
Note: This Question is unanswered, help us to find answer for this one
41. True or False? There is an export to Excel feature for the Task Sheet.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
42. What is another name for a summary task?
Answer
Correct Answer:
Hammock task
Note: This Question is unanswered, help us to find answer for this one
43. The __________ dialog box allows you select up to three fields for three levels of sorts within sorts.
Answer
Correct Answer:
sort
Note: This Question is unanswered, help us to find answer for this one
44. By default, Work is measured in:
Answer
Correct Answer:
Hours
Note: This Question is unanswered, help us to find answer for this one
45. What is a variance thresshold for cost or other acceptable variances called?
Answer
Correct Answer:
Control Thresshold
Note: This Question is unanswered, help us to find answer for this one
46. What is the most accurate way of forecasing EAC and ETC?
Answer
Correct Answer:
ETC based on New Estimates
Note: This Question is unanswered, help us to find answer for this one
47. A calendar can be associated with a:
Answer
Correct Answer:
Resource and Project
Note: This Question is unanswered, help us to find answer for this one
48. To see individual resource details by task, which view should you look at?
Answer
Correct Answer:
Task usage
Note: This Question is unanswered, help us to find answer for this one
49. Which of the following is NOT a valid view?
Answer
Correct Answer:
Resource Chart
Note: This Question is unanswered, help us to find answer for this one
50. To see all tasks for a person, which view should you look at?
Answer
Correct Answer:
Resource usage
Note: This Question is unanswered, help us to find answer for this one
51. What is the process of putting tasks in order of the date they must be completed by?
Answer
Correct Answer:
Nesting
Note: This Question is unanswered, help us to find answer for this one
52. True or False? Custom fields created for a resource can be seen on the task sheet view.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
53. ______ resources affect task scheduling.
Answer
Correct Answer:
Work
Note: This Question is unanswered, help us to find answer for this one
54. You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?
Answer
Correct Answer:
Finish to Finish
Note: This Question is unanswered, help us to find answer for this one
55. True or False? Custom fields created for a task can be seen on the resource sheet view.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
56. Which of the following is NOT a risk-diagramming technique?
Answer
Correct Answer:
Control Diagram
Note: This Question is unanswered, help us to find answer for this one
57. On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.
Answer
Correct Answer:
Schedule
Note: This Question is unanswered, help us to find answer for this one
58. In a fixed units task, if you revise Duration, what happens?
Answer
Correct Answer:
Work is recalculated.
Note: This Question is unanswered, help us to find answer for this one
59. There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?
Answer
Correct Answer:
Create a SF dependency between Task C and Task D.
Note: This Question is unanswered, help us to find answer for this one
60. If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
Answer
Correct Answer:
effort-driven
Note: This Question is unanswered, help us to find answer for this one
61. When assigning a time duration to a task, what is the abbreviation for "months"?
Answer
Correct Answer:
mo
Note: This Question is unanswered, help us to find answer for this one
62. Which of the following is NOT true of deadline dates?
Note: This Question is unanswered, help us to find answer for this one
63. Microsoft Project allows up to ___ baselines per project.
Answer
Correct Answer:
11
Note: This Question is unanswered, help us to find answer for this one
64. When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?
Answer
Correct Answer:
Change their dependency to FF
Note: This Question is unanswered, help us to find answer for this one
65. ______ is an overlap between two tasks that are linked by a dependency.
Answer
Correct Answer:
Lead time
Note: This Question is unanswered, help us to find answer for this one
66. In manual scheduling, changes to which of the following updates task dates?
Answer
Correct Answer:
None of the above
Note: This Question is unanswered, help us to find answer for this one
67. After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?
Answer
Correct Answer:
"Pour the Foundation" Finish-to-Finish with "Build the Frame," and "Mount the Drywall" Finish-to-Start with "Pour the Foundation."
Note: This Question is unanswered, help us to find answer for this one
68. Use the ______ to see how changes to one task affect the rest of the project and to track schedule changes.
Answer
Correct Answer:
Task Inspector
Note: This Question is unanswered, help us to find answer for this one
69. The default task type in Microsoft Project is ____.
Answer
Correct Answer:
fixed units
Note: This Question is unanswered, help us to find answer for this one
70. Which of the following is NOT a valid task constraint?
Answer
Correct Answer:
FBTD - Finish by this date
Note: This Question is unanswered, help us to find answer for this one
71. What is CPI=?
Answer
Correct Answer:
EV/AC
Note: This Question is unanswered, help us to find answer for this one
72. To have Task 10 start three days after Task 9 completes, in the predecessor column, type:
Answer
Correct Answer:
9FS3
Note: This Question is unanswered, help us to find answer for this one
73. The critical path method calculates theoretical early start and late start and finish dates. Critical path have either
Answer
Correct Answer:
Positive or Negative Total Float
Note: This Question is unanswered, help us to find answer for this one
74. True or False? Displaying or removing a group has an effect on the project data.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
75. The ________ tab can be used to set working times, add a holiday to the calendar, and set a baseline.
Answer
Correct Answer:
Project
Note: This Question is unanswered, help us to find answer for this one
76. If you're not certain how Task "Chop the Wood" relates to the work of "Move the Chairs", which dependency type should you create?
Answer
Correct Answer:
FS
Note: This Question is unanswered, help us to find answer for this one
77. True or False? When assigning time for projects, you should also account for non-working time.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
78. What does CPI of 1.1 mean ?
Answer
Correct Answer:
Project is completed ahead of costs by 10%
Note: This Question is unanswered, help us to find answer for this one
79. What is a Scope Manangement plan?
Answer
Correct Answer:
Plan that documents how the project purview will be defined documented verified managed and controlled by the Project Management team.
Note: This Question is unanswered, help us to find answer for this one
80. You have to deliver a new costume sales website by September 30 in time for the Halloween season that begins in mid-October. This is an example of?
Answer
Correct Answer:
Project Constraints
Note: This Question is unanswered, help us to find answer for this one
81. SF dependency implies?
Answer
Correct Answer:
Task 2 must finish before Task 1 can start
Note: This Question is unanswered, help us to find answer for this one
82. The Network Diagram, also known as the ______, shows dependencies between tasks in a graphical manner.
Answer
Correct Answer:
PERT Chart
Note: This Question is unanswered, help us to find answer for this one
83. One of these is NOT a type of resource?
Answer
Correct Answer:
Schedule
Note: This Question is unanswered, help us to find answer for this one
84. If current data consistently differs from baseline data, this is an indication that ______.
Answer
Correct Answer:
your original plan is no longer accurate.
Note: This Question is unanswered, help us to find answer for this one
85. Which of the following is the best way to resolve an issue in which a resource is overallocated?
Answer
Correct Answer:
Changing the resource's availability from 50% to 100%
Note: This Question is unanswered, help us to find answer for this one
86. How much should CPI and SPI be in a project ahead of schedule and costs?
Answer
Correct Answer:
CPI >1, SPI >1
Note: This Question is unanswered, help us to find answer for this one
87. The _______ is used as a template for other calendars.
Answer
Correct Answer:
Base calendar
Note: This Question is unanswered, help us to find answer for this one
88. What is the smallest denomination of time that can be assigned when assigning duration to tasks?
Answer
Correct Answer:
Minutes
Note: This Question is unanswered, help us to find answer for this one
89. If you want to sort your resources by last name so that Brenda Diaz is last on your list and Florian Voss is first on your list, what sort order should you specify?
Answer
Correct Answer:
Descending
Note: This Question is unanswered, help us to find answer for this one
90. When adding a resource to a task, to only use them fifty percent, type this:
Answer
Correct Answer:
Bob[50]
Note: This Question is unanswered, help us to find answer for this one
91. A process that states how formal verfication and acceptance of completed project deliverables will be obtained is documented in the _________.
Answer
Correct Answer:
Scope Management Plan
Note: This Question is unanswered, help us to find answer for this one
92. SS dependency implies?
Answer
Correct Answer:
The work can overlap or proceed in parallel.
Note: This Question is unanswered, help us to find answer for this one
93. If you want to change the hierarchical structure of a task or subtask as part of an outline structure for your project, you need to change the task type or add a deadline date rather than indent or outdent the task.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
94. What character follows an estimated duration?
Answer
Correct Answer:
?
Note: This Question is unanswered, help us to find answer for this one
95. _______ is the length of time by which a task is ahead of schedule and will be completed early if continued.
Answer
Correct Answer:
Slack
Note: This Question is unanswered, help us to find answer for this one
96. What does leveling refer to?
Answer
Correct Answer:
Applying work evenly across resources
Note: This Question is unanswered, help us to find answer for this one
97. The ________ new feature in Microsoft Project 2013 allows you to select any task and see the complete chain of predecessors and successors linked to it.
Answer
Correct Answer:
Task Path Highlighting
Note: This Question is unanswered, help us to find answer for this one
98. Which of the following is NOT a constraint type?
Answer
Correct Answer:
As quickly as possible
Note: This Question is unanswered, help us to find answer for this one
99. The formula to calculate Cost Variance is:
Answer
Correct Answer:
CV = EV - AC
Note: This Question is unanswered, help us to find answer for this one
100. What is a Gantt chart?
Answer
Correct Answer:
A bar chart that illustrates the project schedule
Note: This Question is unanswered, help us to find answer for this one
101. Press the ____ key to display KeyTips over each feature.
Answer
Correct Answer:
ALT
Note: This Question is unanswered, help us to find answer for this one
102. Use the _____ feature to resolve resource conflicts and over-allocations.
Answer
Correct Answer:
Resource Leveling
Note: This Question is unanswered, help us to find answer for this one
103. A _______ is a chart with a series of horizontal lines showing the amount of work done in certain periods of time in relation to the amount of work planned for those periods.
Answer
Correct Answer:
Gantt Chart
Note: This Question is unanswered, help us to find answer for this one
104. Putting 9FF3 in the predecessor column of task 10 causes which of the following to happen?
Answer
Correct Answer:
Task 10 complete three days after task 9 completes
Note: This Question is unanswered, help us to find answer for this one
105. How can you change the duration on a summary task?
Answer
Correct Answer:
You cannot change a summary task duration, you must update the individual subtasks.
Note: This Question is unanswered, help us to find answer for this one
106. What is the best way of doing resource loading in a project having lot of dependencies?
Answer
Correct Answer:
Ensure 1 resource works on only one dependent task and does not move till it is complete
Note: This Question is unanswered, help us to find answer for this one
107. How will a task appear on the Gantt chart when it is a successor of another task?
Answer
Correct Answer:
It will appear indented
Note: This Question is unanswered, help us to find answer for this one
108. Breaking a project into phases and then further dividing into summary tasks and subtasks is called _________ scheduling.
Answer
Correct Answer:
top down
Note: This Question is unanswered, help us to find answer for this one
109. How does Microsoft Project calculate the total work time of a summary task?
Answer
Correct Answer:
Time between the earliest start date and the latest finish date of its subtasks.
Note: This Question is unanswered, help us to find answer for this one
110. If you click Fixed Work in the Task type list, you cannot change the Effort driven setting for the task.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
111. You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?
Answer
Correct Answer:
Finish to Start
Note: This Question is unanswered, help us to find answer for this one
112. The __________ is the approved project schedule and issued to determine the variation between the plan and actual.
Answer
Correct Answer:
baseline
Note: This Question is unanswered, help us to find answer for this one
113. Which of the following is NOT a valid import type for tasks?
Answer
Correct Answer:
SAP ALV grid
Note: This Question is unanswered, help us to find answer for this one
114. _______ scheduling starts at the end of the project and works backwards through the project tasks to the present.
Answer
Correct Answer:
Bottom up
Note: This Question is unanswered, help us to find answer for this one
115. What does PMI stand for?
Answer
Correct Answer:
Project Management Institute
Note: This Question is unanswered, help us to find answer for this one
116. The ______ view, automatically displayed above other views, shows a concise overview of the entire schedule.
Answer
Correct Answer:
Timeline
Note: This Question is unanswered, help us to find answer for this one
117. Payback period is the time it takes to pay back what a project costs. For a project that costs $5,000,000 and delivers increased revenue of $500,000/month, how do you calcuate payback period?
Answer
Correct Answer:
$5,000,000/$500,000 = 10 months
Note: This Question is unanswered, help us to find answer for this one
118. The _______ is the longest duration of linked tasks in a project which must be completed on time for the project to complete on time.
Answer
Correct Answer:
critical path
Note: This Question is unanswered, help us to find answer for this one
119. ______ is a delay between two tasks that are linked by a dependency.
Answer
Correct Answer:
Lag time
Note: This Question is unanswered, help us to find answer for this one
120. How do you mark or indicate a task is a subtask of another?
Answer
Correct Answer:
Indent the subtask
Note: This Question is unanswered, help us to find answer for this one
121. FS dependency implies?
Answer
Correct Answer:
Task 1 must finish before Task 2 can start
Note: This Question is unanswered, help us to find answer for this one
122. What is the default unit of time by which Lag Time is measured?
Answer
Correct Answer:
Days
Note: This Question is unanswered, help us to find answer for this one
123. What is the default duration assigned to an automatically scheduled task?
Answer
Correct Answer:
1 day
Note: This Question is unanswered, help us to find answer for this one
124. Which of the following is NOT a standard field contained within a project?
Answer
Correct Answer:
Quality
Note: This Question is unanswered, help us to find answer for this one
125. What is a run chart?
Answer
Correct Answer:
A line chart that shows trends over time, variation over time, and declines/improvements over time.
Note: This Question is unanswered, help us to find answer for this one
126. By default, Duration is measured in:
Answer
Correct Answer:
Days
Note: This Question is unanswered, help us to find answer for this one
127. ________ are scheduled events that indicate the completion of a major deliverable.
Answer
Correct Answer:
Milestones
Note: This Question is unanswered, help us to find answer for this one
128. ______ is any deviation from the baseline of a project.
Answer
Correct Answer:
Variance
Note: This Question is unanswered, help us to find answer for this one
129. What is a milestone?
Answer
Correct Answer:
A major sub-project in which other tasks may be nexted
Note: This Question is unanswered, help us to find answer for this one
130. Which of the following is a valid task link type?
Answer
Correct Answer:
All of the above
Note: This Question is unanswered, help us to find answer for this one
131. A resource can be created by:
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one
132. A _________ is a deliverable oriented decomposition of a project into smaller components.
Answer
Correct Answer:
Work Breakdown Structure (WBS)
Note: This Question is unanswered, help us to find answer for this one
133. What is a successor activity?
Answer
Correct Answer:
An activity that follows another activity and is dependent on the predecessor activity and usually cannot start without the predecessor activity being finished
Note: This Question is unanswered, help us to find answer for this one
134. MS project is NOT interoperable with:
Answer
Correct Answer:
Mantis bug tracker
Note: This Question is unanswered, help us to find answer for this one
135. A project template has this file extension:
Answer
Correct Answer:
.mpt
Note: This Question is unanswered, help us to find answer for this one
136. Which of the following is NOT a valid duration measurement for a task?
Answer
Correct Answer:
Seconds
Note: This Question is unanswered, help us to find answer for this one
137. The ______ tab on the ribbon allows you to customize text, columns, colors, and other elements of each type of view.
Answer
Correct Answer:
Format
Note: This Question is unanswered, help us to find answer for this one
138. How does Microsoft Project calculate work?
Answer
Correct Answer:
Duration x Units = Work
Note: This Question is unanswered, help us to find answer for this one
139. What does PERT stand for?
Answer
Correct Answer:
Program Evaluation Review Technique
Note: This Question is unanswered, help us to find answer for this one
140. What does the Resource View display?
Answer
Correct Answer:
All of these
Note: This Question is unanswered, help us to find answer for this one