MCQs>Finance & Management>Microsoft Project>You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?
Microsoft Project MCQs
You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?
Answer
Correct Answer: Critical tasks are indicated in red and other tasks are indicated in blue.
Explanation: