MCQs > Finance & Management > Microsoft Project > You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?

Microsoft Project MCQs

You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?

Answer

Correct Answer: Must Finish On

Explanation:

Note: This Question is unanswered, help us to find answer for this one