MCQs > Finance & Management > Microsoft Project > You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?

Microsoft Project MCQs

You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?

Answer

Correct Answer: Finish to Start

Explanation: