MCQs>Finance & Management>Microsoft Project>A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
Microsoft Project MCQs
A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
Answer
Correct Answer: It has changed to 125%.
Explanation: