Correct Answer: Quarters
Explanation:
Note: This Question is unanswered, help us to find answer for this one
Microsoft Project Skill Assessment
Your Skill Level: Poor
Retake Quizzes to improve it
More Microsoft Project MCQ Questions
Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?
You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?
A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
What is another name for a work breakdown structure?
A report for Earned Value Over Time has been requested, You decide to use a Microsoft Project visual report. What values does this report template compare when run?
Which of the following is NOT a valid import type for tasks?
_______ scheduling starts at the end of the project and works backwards through the project tasks to the present.
What does PMI stand for?
The ______ view, automatically displayed above other views, shows a concise overview of the entire schedule.
Payback period is the time it takes to pay back what a project costs. For a project that costs $5,000,000 and delivers increased revenue of $500,000/month, how do you calcuate payback period?