1. Solids in wastewater treatment are removed in ________.

Answer

Correct Answer: Pre-treatment

Note: This Question is unanswered, help us to find answer for this one

2. All of the following are examples of point sources of pollution except ________.

Answer

Correct Answer: Pesticides , herbicides , animal waste , irrigation

Note: This Question is unanswered, help us to find answer for this one

3. ________ is are formed during primary wastewater treatment

Answer

Correct Answer: Sludge

Note: This Question is unanswered, help us to find answer for this one

4. What do aerobic bacteria require for growth?

Answer

Correct Answer: Free (elementary) oxygen

Note: This Question is unanswered, help us to find answer for this one

5. What is the purpose of an Aeration Tank?

Answer

Correct Answer: To inject air into water

Note: This Question is unanswered, help us to find answer for this one

6. What does the process of aeration involve?

Answer

Correct Answer: Bringing about intimate contact between air and a liquid

Note: This Question is unanswered, help us to find answer for this one

7. What is the Activated Sludge Process used for?

Answer

Correct Answer: Disposing of pollution in wastewaters

Note: This Question is unanswered, help us to find answer for this one

8. What does "activated sludge" refer to?

Answer

Correct Answer: A brownish flocculent culture of organisms

Note: This Question is unanswered, help us to find answer for this one

9. When considering using graywater, you might use the water for ________.

Answer

Correct Answer: Flushing toilets.

Note: This Question is unanswered, help us to find answer for this one

10. For treating the sewage of a large city, you will recommend

Answer

Correct Answer: A sedimentation tank and an activated sludge treatment plant

Note: This Question is unanswered, help us to find answer for this one

11. Assertion (A) : Discharging the effluents from the oxidation ponds just up stream of lakes or reservoirs is undesirable. Reason (R) : The discharged algae get settled in the reservoirs and cause anaerobic decomposition and other water qualities.

Answer

Correct Answer: Both A and R are true and R is the correct explanation of A

Note: This Question is unanswered, help us to find answer for this one

12. If 2% solution of a sewage sample is incubated for 5 days at 20°C and depletion of oxygen was found to be 5 ppm, B.O.D. of the sewage is

Answer

Correct Answer: 250 ppm

Note: This Question is unanswered, help us to find answer for this one

13. The screens are fixed

Answer

Correct Answer: At an angle 30° to 60° to the direction of flow

Note: This Question is unanswered, help us to find answer for this one

14. In SI units the power of sound is represented in

Answer

Correct Answer: Watts.

Note: This Question is unanswered, help us to find answer for this one

15. The asbestos cement pipes are generally laid

Answer

Correct Answer: Vertically

Note: This Question is unanswered, help us to find answer for this one

16. If D is the diameter of upper circular portion, the overall depth of a standard egg shaped section

Answer

Correct Answer: 1.5 D

Note: This Question is unanswered, help us to find answer for this one

17. If the diameter of sewer is 225 mm, the gradient required for generating self cleansing velocity, is

Answer

Correct Answer: 1 in 120

Note: This Question is unanswered, help us to find answer for this one

18. If the over land flow from the critical point to the drain is 8 km and the difference in level is 12.4 m, the inlet time is

Answer

Correct Answer: 4 hours

Note: This Question is unanswered, help us to find answer for this one

19. What the house drainage minimum gradient is

Answer

Correct Answer: 1 in 60

Note: This Question is unanswered, help us to find answer for this one

20. House connections to the laterals is generally made by

Answer

Correct Answer: Glazed stonewares

Note: This Question is unanswered, help us to find answer for this one

21. For house drainage minimum gradient is

Answer

Correct Answer: 1 in 60

Note: This Question is unanswered, help us to find answer for this one

22. In olden days the type of section adopted in trunk and out fall sewers was

Answer

Correct Answer: Horse shoe shaped

Note: This Question is unanswered, help us to find answer for this one

23. A rain sanitary sewer is constructed to carry

Answer

Correct Answer: Sanitary sewage

Note: This Question is unanswered, help us to find answer for this one

24. Bio-chemical oxygen demand (BOD) for the first 20 days in generally referred to

Answer

Correct Answer: All of these.

Note: This Question is unanswered, help us to find answer for this one

25. The coagulant widely used for sewage treatment, is

Answer

Correct Answer: Ferric chloride

Note: This Question is unanswered, help us to find answer for this one

26. Clogging of sewers, is caused due to

Answer

Correct Answer: All these

Note: This Question is unanswered, help us to find answer for this one

27. If D is the diameter of upper circular portion, the overall depth of a standard egg shaped section, is

Answer

Correct Answer: 1.5 D

Note: This Question is unanswered, help us to find answer for this one

28. For evaporation and measurement of settlable solids, the apparatus used, is

Answer

Correct Answer: An Imhoff cone

Note: This Question is unanswered, help us to find answer for this one

29. Pick up the correct statement from the following:

Answer

Correct Answer: All these

Note: This Question is unanswered, help us to find answer for this one