MCQs>Finance & Management>PMP - Project Management>Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost is known as:
PMP - Project Management MCQs
Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost is known as:
Answer
Correct Answer: Crashing
Explanation: