MCQs>Finance & Management>PMP - Project Management>In a current project, you use earned value calculations to figure out that you’re going to run $500 over budget if the project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem?
PMP - Project Management MCQs
In a current project, you use earned value calculations to figure out that you’re going to run $500 over budget if the project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem?
Answer
Correct Answer: Knowledge
Explanation: