Adblocker Detected

Adblocker

Quizack provides Online Quiz and Practice MCQs for Free. Please disable your Ad-Blocker so we can earn from ads and keep this project alive.

PMP - Project Management Quiz PMP - Project Management Skill Assessment

ADVERTISEMENT
Quizack provides PMP - Project Management MCQ practice question answers in an interactive format.

PMP - Project Management MCQ

Learn and practice your skills with our MCQ question answers to improve your knowledge. MCQs list

Start Practice with MCQs

PMP - Project Management Online Quiz

Quizack 10 minutes test will assess your knowledge and give you comprehensive results along feedback.

Start Quiz

PMP - Project Management PDF Download

Download Free PMP - Project Management MCQ questions answers PDF to practice and learn while are offline.

Download PDF

 

Used by 100s of Jobseekers and students

Used by 100s of Jobseekers and students

Focused questions for skill assessment

Focused questions for skill assessment

Premium questions with correct answers

Premium questions with correct answers

Related Skill Assessment

Free Sample Questions for PMP - Project Management

A contract to deliver has been signed for the current project you are working on. The customer who has signed the contract has telephoned you to request additional work to be done on the project, which will affect the budget, but not the schedule of the project. What should you do next?

Respond to the customer’s request by explaining the change procedure and asking that he or she submit a request for change

Refuse the request and send a memo to your management explaining the situation

Arrange to meet with the project team to discuss this change

Do what the customer asks you to do and add the additional requirements to the original contract

Answer:
Respond to the customer’s request by explaining the change procedure and asking that he or she submit a request for change

Which of the following is not a responsibility of the Project Manager?

Identify, monitor and respond to risk

Keep project on track in terms of schedule and budget

Provide accurate and timely report on project metrics

Ensure integrity of project team members

Answer:
Ensure integrity of project team members