Senior Design with Water Resources Focus MCQ

1. What does NPV stand for?

Answer

Correct Answer: Net present value

Note: This Question is unanswered, help us to find answer for this one

2. Negative variance occurs when actual project performance is _____ than planned project performance.

Answer

Correct Answer: Worse

Note: This Question is unanswered, help us to find answer for this one

3. Negative variance in time indicates that the project is ____________ than planned.

Answer

Correct Answer: Taking longer

Note: This Question is unanswered, help us to find answer for this one

4. What is the definition of a near-critical path?

Answer

Correct Answer: A series of activities with only small amounts of total float

Note: This Question is unanswered, help us to find answer for this one

5. What is the meaning of "near-critical path"?

Answer

Correct Answer: A series of activities with only small amounts of total float.

Note: This Question is unanswered, help us to find answer for this one

6. What is a near-critical activity?

Answer

Correct Answer: A near-critical activity has only a small amount of total float, or slack time.

Note: This Question is unanswered, help us to find answer for this one

7. What is the definition of a near-critical activity?

Answer

Correct Answer: An activity with only a small amount of total float

Note: This Question is unanswered, help us to find answer for this one

8. What is the definition of motivation?

Answer

Correct Answer: A reason or stimulus that makes a person behave in a certain manner.

Note: This Question is unanswered, help us to find answer for this one

9. What does motivation refer to in management?

Answer

Correct Answer: The desire to pursue personal or organizational goals.

Note: This Question is unanswered, help us to find answer for this one

10. What is the most likely duration?

Answer

Correct Answer: An estimate of the most probable length of time needed to complete an activity.

Note: This Question is unanswered, help us to find answer for this one

11. What is the most probable length of time needed to complete an activity?

Answer

Correct Answer: Most Likely Duration

Note: This Question is unanswered, help us to find answer for this one

12. What is Monte Carlo simulation?

Answer

Correct Answer: A computer-based technique that performs probabilistic forecasting of possible outcomes to facilitate decision making.

Note: This Question is unanswered, help us to find answer for this one

13. What does Monte Carlo simulation/technique do?

Answer

Correct Answer: It is a computer-based technique that performs probabilistic forecasting of possible outcomes to facilitate decision making.

Note: This Question is unanswered, help us to find answer for this one

14. What is the main difference between traditional management and modern project management?

Answer

Correct Answer: Modern project management stresses collective, interdisciplinary knowledge and team consensus over individual leadership.

Note: This Question is unanswered, help us to find answer for this one

15. What is the purpose of a mission statement?

Answer

Correct Answer: To provide direction and guidance

Note: This Question is unanswered, help us to find answer for this one

16. What is a mission statement?

Answer

Correct Answer: A concise enunciation of the goals of an activity or organization.

Note: This Question is unanswered, help us to find answer for this one

17. What does a milestone schedule detail?

Answer

Correct Answer: The time relationships associated with project milestones.

Note: This Question is unanswered, help us to find answer for this one

18. What is the purpose of milestones in project management?

Answer

Correct Answer: To mark progress needed to complete projects successfully

Note: This Question is unanswered, help us to find answer for this one

19. What is the purpose of milestones?

Answer

Correct Answer: To mark progress needed to complete projects successfully.

Note: This Question is unanswered, help us to find answer for this one

20. What is a merge point?

Answer

Correct Answer: A point in a network diagram at which multiple predecessor activities culminate in a single successor activity.

Note: This Question is unanswered, help us to find answer for this one

21. What is a megaproject?

Answer

Correct Answer: A complex, large-scale, and high-investment project.

Note: This Question is unanswered, help us to find answer for this one

22. What is the minimum investment required for a project to be termed as a megaproject?

Answer

Correct Answer: High-investment

Note: This Question is unanswered, help us to find answer for this one

23. What is Maturity?

Answer

Correct Answer: The extent to which an organization's methods, processes, and decisions are standardized and optimized.

Note: This Question is unanswered, help us to find answer for this one

24. What is the purpose of a maturity model?

Answer

Correct Answer: To assess an organization's maturity level according to management best practices

Note: This Question is unanswered, help us to find answer for this one

25. What is a matrix organization?

Answer

Correct Answer: An organization where employees report to more than one boss

Note: This Question is unanswered, help us to find answer for this one

26. What can a matrix organization structure do for employees?

Answer

Correct Answer: Boost employee engagement and cross-field approaches to problem solving

Note: This Question is unanswered, help us to find answer for this one

27. What is a master project file comprised of?

Answer

Correct Answer: Subprojects

Note: This Question is unanswered, help us to find answer for this one

28. What is a master project file?

Answer

Correct Answer: A master project file comprises a number of smaller projects, called subprojects, arranged hierarchically.

Note: This Question is unanswered, help us to find answer for this one

29. What is the goal of management science?

Answer

Correct Answer: To improve organizational decision making through the use of quantitative and scientific research methods

Note: This Question is unanswered, help us to find answer for this one

30. Management processes are carried out at _____ levels within organizations.

Answer

Correct Answer: Multiple

Note: This Question is unanswered, help us to find answer for this one

31. What does the word "management" mean?

Answer

Correct Answer: The act of overseeing planning, personnel, and resources to achieve a goal.

Note: This Question is unanswered, help us to find answer for this one

32. What is a logic network?

Answer

Correct Answer: A chronologically arranged diagram that shows relationships between project activities.

Note: This Question is unanswered, help us to find answer for this one

33. What is the main focus of Linear Scheduling Method?

Answer

Correct Answer: Maximizing resource use

Note: This Question is unanswered, help us to find answer for this one

34. What is the linear sequential model?

Answer

Correct Answer: A linear sequential model moves through a project life cycle's phases systematically and sequentially

Note: This Question is unanswered, help us to find answer for this one

35. What is a line of balance?

Answer

Correct Answer: A graphical technique used to illustrate relationships between repetitive tasks in projects such as building identical housing units.

Note: This Question is unanswered, help us to find answer for this one

36. A life cycle is divided into _____ phases.

Answer

Correct Answer: A number of

Note: This Question is unanswered, help us to find answer for this one

37. What are life cycles divided into?

Answer

Correct Answer: A number of phases

Note: This Question is unanswered, help us to find answer for this one

38. What is the other name for "level of effort"?

Answer

Correct Answer: Support work

Note: This Question is unanswered, help us to find answer for this one

39. What is an example of a level of effort?

Answer

Correct Answer: Maintenance

Note: This Question is unanswered, help us to find answer for this one

40. What is the sum of knowledge gained from project work called?

Answer

Correct Answer: Lessons Learned

Note: This Question is unanswered, help us to find answer for this one

41. What is the goal of Lean six Sigma?

Answer

Correct Answer: Eliminate waste and defects

Note: This Question is unanswered, help us to find answer for this one

42. What is the goal of Lean Manufacturing?

Answer

Correct Answer: Doing more with less

Note: This Question is unanswered, help us to find answer for this one

43. What is the Lead/ Lead time?

Answer

Correct Answer: The amount of time an activity can be brought forward with respect to the activity it is dependent upon.

Note: This Question is unanswered, help us to find answer for this one

44. What is lateral thinking?

Answer

Correct Answer: Lateral thinking involves using a roundabout method to inspire new ideas or solutions.

Note: This Question is unanswered, help us to find answer for this one

45. What is the purpose of a late start date?

Answer

Correct Answer: To avoid delaying the rest of the project.

Note: This Question is unanswered, help us to find answer for this one

46. What is the late start date?

Answer

Correct Answer: The latest possible date a scheduled activity can be started without delaying the rest of the project.

Note: This Question is unanswered, help us to find answer for this one

47. What does Late Finish Date represent?

Answer

Correct Answer: The latest possible date a scheduled activity can be completed without delaying the rest of the project.

Note: This Question is unanswered, help us to find answer for this one

48. What is the definition of "Lag time"?

Answer

Correct Answer: A necessary break or delay between activities

Note: This Question is unanswered, help us to find answer for this one

49. What is a key performance indicator?

Answer

Correct Answer: A metric for measuring project success.

Note: This Question is unanswered, help us to find answer for this one

50. What is the first meeting between a project team and stakeholders called?

Answer

Correct Answer: Kickoff meeting

Note: This Question is unanswered, help us to find answer for this one

51. What is the main purpose of a kickoff meeting?

Answer

Correct Answer: To review project expectations and to build enthusiasm for a project.

Note: This Question is unanswered, help us to find answer for this one

52. What does the word 'Kanban' mean in Japanese?

Answer

Correct Answer: Visual Signal

Note: This Question is unanswered, help us to find answer for this one

53. What is iterative and incremental development?

Answer

Correct Answer: Iterative and incremental development is any combination of the iterative and incremental development approaches.

Note: This Question is unanswered, help us to find answer for this one

54. What does iterative development focus on?

Answer

Correct Answer: Developing products in a series of repeated fixed-time iterations

Note: This Question is unanswered, help us to find answer for this one

55. Which of the following is not a characteristic of Iterative development?

Answer

Correct Answer: Working towards a single deliverable

Note: This Question is unanswered, help us to find answer for this one

56. What does iteration refer to in software development?

Answer

Correct Answer: A fixed time cycle for development work, typically a few weeks long.

Note: This Question is unanswered, help us to find answer for this one

57. What is an issue log?

Answer

Correct Answer: A project management tool used to track issues and resolutions

Note: This Question is unanswered, help us to find answer for this one

58. What does the term 'Issue' refer to in a project?

Answer

Correct Answer: Major problems that cannot be tackled by the project team on their own.

Note: This Question is unanswered, help us to find answer for this one

59. What is ISO 10006?

Answer

Correct Answer: A set of quality management guidelines for projects.

Note: This Question is unanswered, help us to find answer for this one

60. What is an Ishikawa diagram used for?

Answer

Correct Answer: To identify the possible causes of an effect

Note: This Question is unanswered, help us to find answer for this one

61. What is an invitation for bid?

Answer

Correct Answer: A procuring organization's invitation for expressions of interest.

Note: This Question is unanswered, help us to find answer for this one

62. What is an integrated master schedule?

Answer

Correct Answer: A list of all project tasks represented as a networked schedule.

Note: This Question is unanswered, help us to find answer for this one

63. What is an Integrated Master Plan?

Answer

Correct Answer: A project management tool used to break down project work in large, complex projects.

Note: This Question is unanswered, help us to find answer for this one

64. What does integrated change control refer to?

Answer

Correct Answer: The coordination of changes throughout all aspects of a project, including scope, budget, and schedule.

Note: This Question is unanswered, help us to find answer for this one

65. What is integrated assurance?

Answer

Correct Answer: The process of coordinating assurance activities across a number of assurance providers.

Note: This Question is unanswered, help us to find answer for this one

66. What is the process of coordinating assurance activities across a number of assurance providers called?

Answer

Correct Answer: Integrated assurance

Note: This Question is unanswered, help us to find answer for this one

67. What is the process of reviewing and examining the final product to assess compliance to initial requirements and expectations called?

Answer

Correct Answer: Inspection

Note: This Question is unanswered, help us to find answer for this one

68. What are inputs?

Answer

Correct Answer: The information required to start the project management process.

Note: This Question is unanswered, help us to find answer for this one

69. What does the initiation phase involve?

Answer

Correct Answer: Receiving proper authorization and creating a clear definition for the project.

Note: This Question is unanswered, help us to find answer for this one

70. What is the purpose of information distribution?

Answer

Correct Answer: To provide stakeholders with timely information and updates regarding a project.

Note: This Question is unanswered, help us to find answer for this one

71. What is the meaning of "Hypercritical activities"?

Answer

Correct Answer: Critical path activities with negative slack time

Note: This Question is unanswered, help us to find answer for this one

72. What is the purpose of high-level requirements?

Answer

Correct Answer: To explain the major requirements and characteristics of the final product

Note: This Question is unanswered, help us to find answer for this one

73. What is HERMES?

Answer

Correct Answer: A project management method created by the Swiss government

Note: This Question is unanswered, help us to find answer for this one

74. What is hanger?

Answer

Correct Answer: An unplanned break in a network path, usually caused by oversights regarding activities or dependent relationships between activities.

Note: This Question is unanswered, help us to find answer for this one

75. What is the handover?

Answer

Correct Answer: The point at which deliverables are given to users.

Note: This Question is unanswered, help us to find answer for this one

76. What is a hammock activity in a schedule network diagram?

Answer

Correct Answer: A summary activity that represents a number of grouped - but unrelated -smaller activities that occur between two dates

Note: This Question is unanswered, help us to find answer for this one

77. What is GERT?

Answer

Correct Answer: Graphical evaluation and review technique

Note: This Question is unanswered, help us to find answer for this one

78. What does Governance refer to in regards to project management?

Answer

Correct Answer: The structure by which roles and relationships between project team members and an organization’s high-level decision makers are defined.

Note: This Question is unanswered, help us to find answer for this one

79. What is Gold Plating?

Answer

Correct Answer: The practice of incorporating features and improvements that go beyond a product’s agreed-upon characteristics.

Note: This Question is unanswered, help us to find answer for this one

80. What is the practice of incorporating features and improvements that go beyond a product’s agreed-upon characteristics called?

Answer

Correct Answer: Gold plating

Note: This Question is unanswered, help us to find answer for this one

81. What is the process of creating specific, measurable, and attainable goals called?

Answer

Correct Answer: Goal setting

Note: This Question is unanswered, help us to find answer for this one

82. What does SMART stand for in relation to goal setting?

Answer

Correct Answer: Specific, Measurable, Attainable, Relevant, Time-based

Note: This Question is unanswered, help us to find answer for this one

83. What is a gate?

Answer

Correct Answer: A checkpoint at which decisions are made about whether and how to continue with the project.

Note: This Question is unanswered, help us to find answer for this one

84. What is a gate in project management?

Answer

Correct Answer: A checkpoint at which decisions are made regarding whether and how to continue with the project.

Note: This Question is unanswered, help us to find answer for this one

85. What is a Gantt chart?

Answer

Correct Answer: A Gantt chart is a type of bar chart that shows all the tasks constituting a project.

Note: This Question is unanswered, help us to find answer for this one

86. What is the Gantt chart used for?

Answer

Correct Answer: Shows all the tasks constituting a project

Note: This Question is unanswered, help us to find answer for this one

87. What is a future state?

Answer

Correct Answer: A detailed representation of the ideal condition of a company’s business processes after improvement.

Note: This Question is unanswered, help us to find answer for this one

88. What are functional requirements?

Answer

Correct Answer: The working characteristics of a product.

Note: This Question is unanswered, help us to find answer for this one

89. What is the main focus of a functional organization?

Answer

Correct Answer: Groups based on specialty areas

Note: This Question is unanswered, help us to find answer for this one

90. What is functional organization?

Answer

Correct Answer: An organization which organizes and manages staff members in groups based on specialty areas.

Note: This Question is unanswered, help us to find answer for this one

91. What is a functional manager?

Answer

Correct Answer: The individual in charge of all activities carried out by a particular functional department within an organization.

Note: This Question is unanswered, help us to find answer for this one

92. What is the term for when authorized stakeholders sign off on a product?

Answer

Correct Answer: Formal acceptance

Note: This Question is unanswered, help us to find answer for this one

93. What does formal acceptance mean?

Answer

Correct Answer: The step at which authorized stakeholders sign off on a product, indicating that it meets their expectations.

Note: This Question is unanswered, help us to find answer for this one

94. What does forecast mean?

Answer

Correct Answer: A prediction or estimation of future project status based on available information.

Note: This Question is unanswered, help us to find answer for this one

95. What is the goal of focused improvement?

Answer

Correct Answer: To optimize a system by addressing one limiting factor at a time.

Note: This Question is unanswered, help us to find answer for this one

96. What is the focus of a focused improvement strategy?

Answer

Correct Answer: One limiting factor at a time

Note: This Question is unanswered, help us to find answer for this one

97. What type of contract pays an agreed-upon fee?

Answer

Correct Answer: Fixed price contract

Note: This Question is unanswered, help us to find answer for this one

98. What is a fixed price contract?

Answer

Correct Answer: A fixed price contract pays an agreed-upon fee and does not incorporate other variables, such as time and cost.

Note: This Question is unanswered, help us to find answer for this one

99. How is earned value calculated in the fixed formula method?

Answer

Correct Answer: By splitting a work package budget between the start and completion milestones of a work package

Note: This Question is unanswered, help us to find answer for this one

100. What is a task in which the time required for completion is fixed called?

Answer

Correct Answer: Fixed duration

Note: This Question is unanswered, help us to find answer for this one