MCQs > Engineering & Manufacturing > Mechanical Engineering > In a programmed evaluation and review technique, if the slack of an activity is negative, then what can be stated for the project completion?

Mechanical Engineering MCQs

In a programmed evaluation and review technique, if the slack of an activity is negative, then what can be stated for the project completion?

Answer

Correct Answer: Additional resources are required to complete the project in time.

Explanation:

Note: This Question is unanswered, help us to find answer for this one