MCQs > Finance & Management > PMP - Project Management > You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?

PMP - Project Management MCQs

You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?

Answer

Correct Answer: Look at other tasks in the schedule and see which ones should be reduced to allow time for this problem to be worked out

Explanation:

Note: This Question is unanswered, help us to find answer for this one

PMP - Project Management Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it

search

PMP - Project Management Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it