Project Management MCQ

1. Software vendors usually bundle fixes of low-priority problems into larger groups called ________.

Answer

Correct Answer: Service packs

Note: This Question is unanswered, help us to find answer for this one

2. Software designed specifically for managing real estate is an example of ________ software.

Answer

Correct Answer: Vertical market

Note: This Question is unanswered, help us to find answer for this one

3. In project procurement management, an output of the _____ monitoring and controlling process.

Answer

Correct Answer: Change requests

Note: This Question is unanswered, help us to find answer for this one

4. A project triangle shows three legs: _____.

Answer

Correct Answer: Project cost, scope, and time

Note: This Question is unanswered, help us to find answer for this one

5. According to thamhain and wilemon, _____ is the ability to improve a workers position.

Answer

Correct Answer: Promotion

Note: This Question is unanswered, help us to find answer for this one

6. A ___________ chart is a histogram that can help you identify and prioritize problem areas.

Answer

Correct Answer: Pareto

Note: This Question is unanswered, help us to find answer for this one

7. _____ involves doing whatever you can to make sure the positive risk happens.

Answer

Correct Answer: Risk exploitation

Note: This Question is unanswered, help us to find answer for this one

8. One of the main outputs of the _____ process is a cost baseline.

Answer

Correct Answer: Cost budgeting

Note: This Question is unanswered, help us to find answer for this one

9. A project manager?s planning _____.

Answer

Correct Answer: Includes informing management, users, and the project team about the progress of the projectproject cost, scope, and time

Note: This Question is unanswered, help us to find answer for this one

10. In organizational culture, control refers to _____.

Answer

Correct Answer: The degree to which rules, policies, and direct supervision are used to oversee employee behavior

Note: This Question is unanswered, help us to find answer for this one

11. A(n) _____ is a document used to solicit proposals from prospective suppliers.

Answer

Correct Answer: RFP

Note: This Question is unanswered, help us to find answer for this one

search