Which of the following is a part of Test Closure Activities?

i. Checking which planned deliverables have been delivered

ii. Defect report analysis.

iii. Finalizing and archiving testware.

iv. Analyzing lessons.


i, ii, iv are true and iii is false

i , ii , iii are true and iv is false

i, iii, iv are true and ii is false 

All of above are true

Answer:

i, iii, iv are true and ii is false 