MCQs > IT & Programming > Software Testing > Which of the following activities would NORMALLY be undertaken during test planning?a. Scheduling test analysis and design.b. Designing Test Conditions.c. Monitoring test progress.d. identifying the objectives of testing.e. Evaluating test tools.f. Selecting test metrics for monitoring and control.

Software Testing MCQs

Which of the following activities would NORMALLY be undertaken during test planning?

a. Scheduling test analysis and design.

b. Designing Test Conditions.

c. Monitoring test progress.

d. identifying the objectives of testing.

e. Evaluating test tools.

f. Selecting test metrics for monitoring and control.


Answer

Correct Answer:

a. d and f

Explanation:

Note: This Question is unanswered, help us to find answer for this one

Software Testing Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it

search

Software Testing Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it