Consider a project in which the development team is required to build a compiler. The team has never written a compiler and is not sure about the technical solutions of project. Which of the following models should be used in such a situation so that the issue is resolved and the best product is obtained?
Correct Answer:
Prototype model
Explanation:
Note: This Question is unanswered, help us to find answer for this one