MCQs > Finance & Management > PMP - Project Management > A contract to deliver has been signed for the current project you are working on. The customer who has signed the contract has telephoned you to request additional work to be done on the project, which will affect the budget, but not the schedule of the project. What should you do next?

PMP - Project Management MCQs

A contract to deliver has been signed for the current project you are working on. The customer who has signed the contract has telephoned you to request additional work to be done on the project, which will affect the budget, but not the schedule of the project. What should you do next?

Answer

Correct Answer: Respond to the customer’s request by explaining the change procedure and asking that he or she submit a request for change

Explanation:

Note: This Question is unanswered, help us to find answer for this one

PMP - Project Management Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it

search

PMP - Project Management Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it