MCQs>Finance & Management>Operations Research>The crash cost and the crash time of a project is $50000 and 30 days respectively. The normal cost and the normal time of the same project is $150000 and 180 days respectively. Calculate the cost slope.
Operations Research MCQs
The crash cost and the crash time of a project is $50000 and 30 days respectively. The normal cost and the normal time of the same project is $150000 and 180 days respectively. Calculate the cost slope.
Answer
Correct Answer: 0.33
Explanation: