Correct Answer: Open as read-only and allow others to use the pool.
Explanation:
Note: This Question is unanswered, help us to find answer for this one
Microsoft Project Skill Assessment
Your Skill Level: Poor
Retake Quizzes to improve it
More Microsoft Project MCQ Questions
On your computer, Automatically add new views, tables. filters. and groups to the global is selected. You are using a custom filter that you created in one of your schedules, and you modify it to better meet your needs. You now notice that this modification is not available in other schedules. How do you fix this?
A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have?
A project currently has a software developer performing two tasks at the same time. The first task is 5 days long; the second task is day long. It has been decided that the developer can take some time to work on the shorter task in the middle the longer task without impacting the schedule. What is the best way to this!
You want to change the view of the timescale on Gantt chart to be more granular. How many tiers does the timescale support?
You are working with two project files. You want the second project to contain some of the same tasks, along with their work assignments, as the first project. You Choose to copy the tasks between the projects. What else is copied along with the task when performing basic copy and paste action?
By default, Duration is measured in:
________ are scheduled events that indicate the completion of a major deliverable.
______ is any deviation from the baseline of a project.
What is a milestone?
Which of the following is a valid task link type?