MCQs>Finance & Management>Microsoft Project>You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?
Microsoft Project MCQs
You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?
Answer
Correct Answer: Finish to Finish
Explanation: