Correct Answer: Changing the resource's availability from 50% to 100%
Explanation:
Note: This Question is unanswered, help us to find answer for this one
Microsoft Project Skill Assessment
Your Skill Level: Poor
Retake Quizzes to improve it
More Microsoft Project MCQ Questions
If current data consistently differs from baseline data, this is an indication that ______.
One of these is NOT a type of resource?
The Network Diagram, also known as the ______, shows dependencies between tasks in a graphical manner.
SF dependency implies?
You have to deliver a new costume sales website by September 30 in time for the Halloween season that begins in mid-October. This is an example of?
There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?
If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
When assigning a time duration to a task, what is the abbreviation for "months"?
Which of the following is NOT true of deadline dates?
Microsoft Project allows up to ___ baselines per project.