MCQs>Finance & Management>Microsoft Project>When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?
Microsoft Project MCQs
When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?
Answer
Correct Answer: Change their dependency to FF
Explanation: