MCQs > Finance & Management > Microsoft Project > A resource's hours have increased over the span of five days for a particular task. The duration has not changed, and the task is effort driven. What element can you add to the Task Usage view to see what has changed?

Microsoft Project MCQs

A resource's hours have increased over the span of five days for a particular task. The duration has not changed, and the task is effort driven. What element can you add to the Task Usage view to see what has changed?

Answer

Correct Answer: Add a column for the Peak value.

Explanation:

Note: This Question is unanswered, help us to find answer for this one

Microsoft Project Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it

search

Microsoft Project Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it