MCQs > Finance & Management > Microsoft Project > A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?

Microsoft Project MCQs

A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?

Answer

Correct Answer: Use the Leveling Gantt view adjust the edays field for the second task.

Explanation: