MCQs>Finance & Management>Microsoft Project>A report for Earned Value Over Time has been requested, You decide to use a Microsoft Project visual report. What values does this report template compare when run?
Microsoft Project MCQs
A report for Earned Value Over Time has been requested, You decide to use a Microsoft Project visual report. What values does this report template compare when run?
Answer
Correct Answer: Earned Value. Planned Value, and Actual
Explanation: