MCQs > Finance & Management > Microsoft Project > A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays?

Microsoft Project MCQs

A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays?

Answer

Correct Answer: On the Project tab, click Move Project.

Explanation: