MCQs>Finance & Management>Microsoft Project>A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have?
Microsoft Project MCQs
A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have?
Answer
Correct Answer: Five
Explanation: