linked linked linkedin whatsapp remove
Feedback

Angular 6

Which of the following is not an option to achieve reliable cost and effort estimate?

Base estimates on similar projects that have already been completed
Use one or more empirical models for software cost and effort estimation
Use relatively simple decomposition techniques to generate project cost and effort estimates.
The ability to translate the size estimate into human effort, calendar time, and dollars.

Answer:
The ability to translate the size estimate into human effort, calendar time, and dollars.

Note: This Question is unanswered, help us to find answer for this one