MCQs > Finance & Management > Accounting Assets And Revenue > Late in Year 1, XYZ Company signs a contract to construct a bridge for the Florida Dept. of Transportation. The contract price is $42,000,000. The costs during the 3-year construction period are as follows: Year 2: $10,000,000 Year 3: $15,000,000 Year 4: $5,000,000 If XYZ Company recognizes income under the percentage-of-completion method, how much income would they recognize on the bridge contract in Year 4?

Accounting Assets And Revenue MCQs

Late in Year 1, XYZ Company signs a contract to construct a bridge for the Florida Dept. of Transportation. The contract price is $42,000,000. The costs during the 3-year construction period are as follows:
Year 2: $10,000,000
Year 3: $15,000,000
Year 4: $5,000,000
If XYZ Company recognizes income under the percentage-of-completion method, how much income would they recognize on the bridge contract in Year 4?

Answer

Correct Answer: $2,000,000

Explanation:

Note: This Question is unanswered, help us to find answer for this one

Accounting Assets And Revenue Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it

More Accounting Assets And Revenue MCQ Questions

search

Accounting Assets And Revenue Skill Assessment

Overall Skill Level-Poor

Your Skill Level: Poor

Retake Quizzes to improve it