MCQs>IT & Programming>Software Engineering>The process to check that the completely developed system conforms to its requirement specifications is called __________, and the process to check that the output of one phase conforms to the previous phase during software development is known as_____________.
Software Engineering MCQs
The process to check that the completely developed system conforms to its requirement specifications is called __________, and the process to check that the output of one phase conforms to the previous phase during software development is known as_____________.
Answer
Correct Answer: validation, verification
Explanation: