Successor Task is a task that follows a given task.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Amount of time tasks may be delayed without delaying the project end date; also known as float is known as :
Answer
Correct Answer:
Slack
Note: This Question is unanswered, help us to find answer for this one
A task that must be completed before following tasks can be started is called ___________ .
Answer
Correct Answer:
Predecessor Task
Note: This Question is unanswered, help us to find answer for this one
Precedence network is a network of arcs and nodes used to represent the precedence relationships between tasks.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Milestones are tasks that require zero time, have no associated direct costs, and are used to represent important events in the life of a project.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
LP in Programming of Project Management stands for:
Answer
Correct Answer:
Linear Programming
Note: This Question is unanswered, help us to find answer for this one
Gantt chart is a bar chart where the duration of each task is represented by a horizontal bar.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Part of the CPM calculations through a project’s precedence network that proceed from the starting node to the ending node is known as:
Answer
Correct Answer:
Forward Pass
Note: This Question is unanswered, help us to find answer for this one
___________ is the amount of time tasks in a precedence network may be delayed without delaying the project end date; also known as slack.
Answer
Correct Answer:
Float
Note: This Question is unanswered, help us to find answer for this one
A methodology used to calculate a project schedule in a deterministic project precedence network based on the longest path from the starting to the ending milestone is called ____________.
Answer
Correct Answer:
Critical Path Method (CPM)
Note: This Question is unanswered, help us to find answer for this one
Critical Path is the longest path from the starting milestone to the ending milestone in a project’s precedence network.
Answer
Correct Answer:
True
Note: This Question is unanswered, help us to find answer for this one
Part of the CPM calculations where you start at the end node of the project’s precedence network and move backward through the network is called ____________ .
Answer
Correct Answer:
Backward Pass
Note: This Question is unanswered, help us to find answer for this one
A graph consisting of nodes connected by unidirectional arcs that contains no cycles is known as :
Answer
Correct Answer:
Acyclic Directed Network
Note: This Question is unanswered, help us to find answer for this one
Activity-on-Node (AON) Network is a visual representation of a project as a network using arrows or arcs to represent tasks and nodes to represent events/milestones.
Answer
Correct Answer:
False
Note: This Question is unanswered, help us to find answer for this one
Activity-on-Arc (AOA) Network is a visual representation of a project as a network using arrows or arcs to represent tasks and nodes to represent ______________ .
Answer
Correct Answer:
Both
Note: This Question is unanswered, help us to find answer for this one