MCQs>Finance & Management>Microsoft Project>You are using work breakdown structure (WBS) codes for an in-progress project. Due to some schedule changes, tasks have been moved around, which has modified the WBS. How do you fix the WBS codes?
Microsoft Project MCQs
You are using work breakdown structure (WBS) codes for an in-progress project. Due to some schedule changes, tasks have been moved around, which has modified the WBS. How do you fix the WBS codes?
Answer
Correct Answer: From the Project tab on the ribbon, click WBS > Renumber.
Explanation: