MCQs>Finance & Management>Microsoft Project>You are preparing a meal comprising a main dish and multiple side dishes. You want the finish of the main dish to drive the finish of the side dishes. The main dish will start before and take longer than the side dishes. You need to create a link from the main dish to each of the side dishes. Which link type is appropriate?
Microsoft Project MCQs
You are preparing a meal comprising a main dish and multiple side dishes. You want the finish of the main dish to drive the finish of the side dishes. The main dish will start before and take longer than the side dishes. You need to create a link from the main dish to each of the side dishes. Which link type is appropriate?
Answer
Correct Answer: Finish-to-Finish(FF)
Explanation:
Note: This Question is unanswered, help us to find answer for this one