Comptia Project + Project Management

Logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity

Identify risks (Process)
Project team directory
Start to start (SS)
Data date

Answer:
Start to start (SS)