MCQs > Engineering & Manufacturing > Civil Engineering MCQs > Estimation and Costing MCQs

Estimation and Costing MCQ

As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

Answer

Correct Answer: All these

Note: This Question is unanswered, help us to find answer for this one

The order of booking dimensions is

Answer

Correct Answer: Length, breadth, height

Note: This Question is unanswered, help us to find answer for this one

Pick up the correct statement from the following:

Answer

Correct Answer: All these

Note: This Question is unanswered, help us to find answer for this one

In the mid-section formula

Answer

Correct Answer: The mean depth is the average of depths of two consecutive sections

Note: This Question is unanswered, help us to find answer for this one

For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

Answer

Correct Answer: 0.274 m3

Note: This Question is unanswered, help us to find answer for this one

The height of the sink of wash basin above floor level is kept

Answer

Correct Answer: 75 cm to 80 cm

Note: This Question is unanswered, help us to find answer for this one

The expected out turn of 2.5 cm cement concrete floor per manson per day

Answer

Correct Answer: 7.5 sqm

Note: This Question is unanswered, help us to find answer for this one

While preparing a detailed estimate

Answer

Correct Answer: Volume should be measured correct to O.Olcum

Note: This Question is unanswered, help us to find answer for this one

The plinth area of a building not includes

Answer

Correct Answer: Area of the walls at the floor level

Note: This Question is unanswered, help us to find answer for this one

The expected out turn of 12 mm plastering with cement mortar is

Answer

Correct Answer: 8.0 sq m

Note: This Question is unanswered, help us to find answer for this one

The minimum width of a septic tank is taken

Answer

Correct Answer: 75 cm

Note: This Question is unanswered, help us to find answer for this one

The item of the brick structure measured in sq.m, is

Answer

Correct Answer: Broken glass coping

Note: This Question is unanswered, help us to find answer for this one

A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

Answer

Correct Answer: 27, 500 m3

Note: This Question is unanswered, help us to find answer for this one

In case of laying gullies, siphons, intercepting traps, the cost includes

Answer

Correct Answer: All of these.

Note: This Question is unanswered, help us to find answer for this one

Brick walls are measured in sq. m if the thickness of the wall is

Answer

Correct Answer: 20 cm

Note: This Question is unanswered, help us to find answer for this one

The concrete work for the following part of the building of specified thickness is measured in square metres

Answer

Correct Answer: All these

Note: This Question is unanswered, help us to find answer for this one

The correct prismoidal formula for volume is

Answer

Correct Answer: D/3 [first area + last area + 4 ∑ Even area + 2 ∑ odd areas]

Note: This Question is unanswered, help us to find answer for this one

Pick up the correct statement in case of water supply.

Answer

Correct Answer: Pipes laid in trenches and pipes fixed to walls are measured separately

Note: This Question is unanswered, help us to find answer for this one

Pick up the incorrect statement regarding a master trap from the following :

Answer

Correct Answer: The water seal is less than that of ordinary traps.

Note: This Question is unanswered, help us to find answer for this one

Pick up the excavation where measurements are made in square metres for payment.

Answer

Correct Answer: Both Ordinary cuttings up to 1 m and surface dressing up to 15 cm depths

Note: This Question is unanswered, help us to find answer for this one